Close movie

After Jernbro helped replace a control system, maintenance manager Gert Holgersson at Parker in Trollhättan only has good things to say about the cooperation.

“The whole process has been so smooth. So professional. We have had peace of mind all the time and they really know what they are doing.”

It’s not the first time Parker in Trollhättan has cooperated with Jernbro and it won’t be the last. On our visit, the whole group who worked on replacing the control system were incredibly satisfied with the joint project.

”We have cooperated with Jernbro for many years. Among other things we have sent motors for emergency repairs knowing that we could rely on them. It is quite natural to turn to a supplier you know, but of course we did a thorough evaluation before they were given the assignment,” says Stefan Rydin, project manager at Parker.

One day it became clear that the machine that milled the splines on the shafts was in need of attention. Spare parts for the control system were no longer available and it had already been repaired so many times that it was at the end of the road. The question was whether to invest in a new machine, outsource the milling of the spines to an external supplier or rebuild the existing machine.

After a thorough evaluation, it was decided to contact a number of suppliers and ask them for a quote. The order finally went to Jernbro in Skövde.

“They had the competence to perform all operations; replace the control system and all the hydraulics, install new electronics and renovate the motors. The challenge for all of us at Parker was to build up a stock so that we had enough shafts during downtime. We expected a downtime of four weeks.

When the renovation work was started, there was a stock of 4,000 shafts in 50 different versions, which covered all needs during downtime.

 

THE WORK STEP BY STEP

“We started as soon as we got the order. We did risk analyses, took stock of the machine and ordered the right components and hardware to be well prepared and minimize downtime,” describes Rolf Andersson, sales representative at Jernbro.

They broke down the work into a detailed plan almost hour for hour – for what should be done and when.

“We had also scheduled extra time on Saturdays and Sundays in case anything unexpected happened, but we never needed to use this time.

The process started with Jernbro taking stock of the machine, then they ordered all the parts and started the design work in Skövde and on site in Trollhättan. A few months later the machine was shut down and the actual transformation began.

“During the first seven to eight days we dismantled, renovated and began the installation of all the new parts,” says Rolf Andersson.

During the project time, the working group from Parker visited Skövde and they saw how the work was progressing. Before the start, all staff involved from Parker attended courses in operation, service and maintenance on a similar control system.

“We started up carefully during the second week with an I/O test and systematically went through and verified the installation to get everything working again,” says Rolf Andersson.

“After the optimization, and some requests for changes including programming, they gradually began to manufacture the parts in the machine and already on the Monday in the fifth week we were ready to go.”

“After the renovation, the machine had a totally different capability. The quality was much better – we have that documented – and the control system and servomotor were running much more smoothly,” says Ronald Svärdh, production technician.

Other advantages are a shorter conversion time, the machine is easier to work with and precision is higher. Moreover, we have a better idea of the lifetime of the tool thanks to functions in the new control system and this means we can fully utilize the tools.

“Jernbro promised that capability would be the same or better after commissioning. Our follow-up shows that capability has increased by 30 per cent. They also promised an availability of 98 per cent and we are following that up now. So far, it looks good,” says Stefan Rydin at Parker.

He notes that the whole process took about four months from order to commissioning and both parties have been very pleased with the cooperation. They usually say that you save about 50 per cent with a total renovation compared to investing in a new machine, which Stefan Rydin thinks is a reasonable estimate.

”We expect to save around three million kronor with Jernbro’s rebuild, compared with investing in a new machine,” concludes Stefan Rydin.

”We expect to save around three million kronor with Jernbro’s rebuild, compared with investing in a new machine.”
Stefan Rydin, Project Manager at Parker

curious to know more?

Select contact

Mats Ahrling, Business Developer Component Servicing Skövde +46 10-483 01 95 Email

Contact undefined

    You might also be interested in

    Engineering

    Complicated move against a tight deadline

    Last spring SSAB bought some lines for roll forming that were in Fagersta. But they needed to be moved around sixty kilometres north – to Borlänge.

    Maintenance

    Survey: Better production flow with condition-based maintenance

    We asked 100 maintenance managers in 10 different industries with more than 50 employees if they work with condition-based maintenance. The result is clear.

    share this