Plant back in operation

When energy must be produced, security of supply is essential – even when the boiler fails just before Christmas in Denmark.

During periods of high load, there is no room for prolonged shutdowns, and a failure of key components can have a direct impact on both production and supply.

This places demands on rapid mobilization, technical oversight, and safe execution from day one.

Challenge

Shortly before the Christmas break, a valued customer experienced a rupture in the pipes to the boiler header box.

The task was critical in several respects:
Timing during peak demand, welding in alloyed materials, stringent quality requirements, and a difficult location.

Solution

We mobilized our own and contracted specialists in boiler welding and pipe fitting.

Together with the site foremen, they formed a strong team that safely managed critical deliveries and subcontractors throughout the process.

At the same time, the documentation department supported the work and ensured traceability and document control.

Results

More than 50 critical welds and over 20 pressure tests were completed – day and night.

This ensured that the plant could quickly return to operation.

Why choose Jernbro

  • For critical tasks
  • Under complex and demanding conditions
  • When metallurgical knowledge and welding expertise are crucial
  • When requirements are high – and there is no room for error
Business inquiries

By submitting this form, you consent to Jernbro processing your personal data in order to handle your request. Your information will be used in accordance with our privacy policy, where you can also read more about how we process personal data and your rights under applicable data protection laws (GDPR).

CONTACT US today

We value a good conversation – so please call if you have questions, need help or want to discuss an idea.

If you prefer to write to us, you can use the customer contact form – and we will get back to you quickly.
headshot of Chano Thaarup Erlandsen

Chano Thaarup Erlandsen

Head of Projects

cth@jernbro.dk

+45 2575 1049